On-Premise AI Infrastructure: Servers, Power and Cooling

9 min read

Planning on-premise AI infrastructure for LLMs is mostly a facilities and operations exercise once the GPU is chosen. The card decides what you can run; the server, power, cooling, network and software decide whether it gets installed and stays up.

The short version for most inference deployments: buy PCIe servers with 2-4 GPUs unless you need models above about 100B parameters, budget 3-5 kW per 4-GPU server and about 10-14 kW per 8-GPU server, stay on air cooling unless your facility already runs liquid, and use ordinary 25 GbE networking. Fast interconnects such as InfiniBand are for training and for models split across servers, which inference rarely needs.

This post assumes you already know which GPU you want. If not, read the best GPU for LLM inference first, and GPU memory for LLM inference to size the card.

Server form factors for on-prem LLM deployment

You will see three shapes of GPU server in quotes.

Form factor GPUs GPU interconnect Typical cards Good for
Workstation or 1-2U server 1-2 PCIe L4, L40S, RTX PRO 6000 Pilots, models up to ~32B, one team
4-GPU PCIe server (2-4U) 4 PCIe, optional NVLink bridges L40S, H100 NVL, H200 NVL, RTX PRO 6000 70B models, several models side by side
8-GPU HGX or DGX (8-10U) 8 NVLink across all 8 H100, H200, B200 SXM 100B+ models, 671B MoE, heavy concurrency

The PCIe server is the default for inference. You can mix models across cards, replace a failed card yourself and buy from any server vendor. The H100 NVL and H200 NVL are dual-slot, air-cooled PCIe cards that also support NVLink bridges between cards (600 GB/s on the H100 NVL).

The 8-GPU HGX baseboard (sold as NVIDIA DGX, or by Dell, HPE, Supermicro, Lenovo and others under their own names) uses SXM modules joined by NVLink. That matters when one model is spread across all eight GPUs, because every generated token moves data between them. The DGX H100/H200 has 640 GB of GPU memory with H100 or 1,128 GB with H200, enough for the very large open models. If your largest model fits on one or two cards, the 8-GPU box is mostly paying for interconnect you will not use.

One trap with workstations: data-center cards such as the L40S are passively cooled. They have no fan and rely on the server pushing air through them, so they belong in a chassis the vendor has certified for that card, not a desktop tower.

AI server power requirements

Vendor power figures for the cards and systems people deploy:

Component Maximum power Source
L4 72 W NVIDIA L4
L40S 350 W NVIDIA L40S
H100 NVL (PCIe) 350-400 W, configurable NVIDIA H100
RTX PRO 6000 Blackwell Server Edition Up to 600 W, configurable NVIDIA RTX PRO 6000
H200 NVL (PCIe) Up to 600 W, configurable NVIDIA H200
H100 or H200 SXM Up to 700 W, configurable NVIDIA H100 and H200 pages
AMD MI300X (OAM) 750 W AMD MI300X
DGX H100/H200 system (8 GPUs) 10.2 kW, six 3.3 kW supplies DGX H100/H200 user guide
DGX B200 system (8 GPUs) ~14.3 kW NVIDIA DGX B200

For PCIe servers there is no single vendor figure, so estimate: add up the GPU maximums, then add roughly 1-1.5 kW for CPUs, memory, drives, NICs and fans. That allowance is our estimate for a dual-socket server; take the real number from the vendor's power calculator for the exact configuration you are quoted. Four H200 NVL cards at 600 W are 2.4 kW, so the server lands around 3.5-4 kW. Four L40S cards are 1.4 kW, so about 2.5-3 kW.

Then compare that to the rack. Two DGX H100 systems in one rack need 20.4 kW at peak. Many existing enterprise racks were provisioned for general servers at a fraction of that, so ask facilities three questions before you order: the power budget per rack, the circuit type (the DGX expects 200-240 V input), and whether the upstream UPS and PDU can carry the load with redundancy. The answer often decides the form factor for you: four 4-GPU servers spread across two racks may fit where one 8-GPU server does not.

Plan circuits for the nameplate even though inference rarely runs flat out: a burst of long prompts gets close.

Cooling: air or liquid

Every watt becomes heat. A 10.2 kW server rejects about 34,800 BTU per hour (1 kW is about 3,412 BTU/hr), which is what the room's cooling has to remove.

Air cooling still covers most inference deployments. The PCIe cards above, including the H200 NVL, are sold as air-cooled parts, and 8-GPU H100 and H200 servers are widely sold in air-cooled versions. At this density you need airflow discipline: aisle containment, blanking panels and enough intake margin that GPUs do not throttle in summer.

Liquid cooling becomes necessary at rack scale. NVIDIA describes the 72-GPU GB200 NVL72 as a "rack-scale, liquid-cooled design", and some cards, such as the RTX PRO 6000 Blackwell, come in a liquid-cooled single-slot version. Direct liquid cooling needs coolant distribution units and facility water, and retrofitting them is a project of its own. For most inference deployments, that is a reason to choose more air-cooled servers rather than fewer dense ones.

Networking for LLM inference

Inference traffic is small. A request is a few kilobytes of text and a streamed answer is a few kilobytes more, so even thousands of requests per minute barely register on a 10 GbE link. The network matters in three other places:

  • Loading models. A 40 GB model file takes about 32 seconds to copy at 10 Gb/s line rate and about 13 seconds at 25 Gb/s. If you restart or swap models often, or pull weights from a shared store, 25 GbE is the sensible default.
  • Spanning servers. If one model is too big for a single server and must be split across two, the GPUs exchange data every token. That is where 400 Gb/s InfiniBand or RoCE earns its cost. The DGX H100/H200 carries eight ConnectX-7 adapters at up to 400 Gb/s each for this reason.
  • Training and fine-tuning. These move gradients between GPUs and servers constantly and need the fast fabric too.

If every model you serve fits inside one server, you do not need InfiniBand. Put the servers on 25 GbE, add a separate 1 GbE management network for the baseboard controllers, and spend the savings on GPU memory.

Storage for model weights

Model weights are large, read-mostly files. A 70B model at 4-bit is about 42 GB, at 8-bit about 75 GB, and a full-size model such as DeepSeek R1 at FP8 is roughly 700 GB. You will keep several models and at least one previous version of each.

Local NVMe on every GPU server is the simplest answer, because loading from local disk is the fastest path into GPU memory. NVIDIA ships the DGX H100/H200 with eight 3.84 TB NVMe drives (about 30 TB) as a data cache beside its OS drives, which gives a sense of scale. For a PCIe server, 4-8 TB of NVMe is a reasonable starting point. Keep a shared NFS or object store as the source of truth and copy from it; do not serve straight off network storage.

Air-gapped sites need extra capacity for staging copies. Our air-gapped LLM deployment post has the disk budget and checksum process.

On-premise AI infrastructure sizing table

These are planning starting points for inference. Power for PCIe tiers is estimated as described above; the 8-GPU figures are NVIDIA's system maximums.

Small Medium Large
Typical use One department, pilot or production for up to ~50 users Several teams, 70B-class models, a few models at once Company-wide service or 100B+ models
Hardware 1 server, 1-2 L40S or RTX PRO 6000 2 servers with 4 GPUs each (H100 NVL, H200 NVL or RTX PRO 6000) 1-2 HGX/DGX servers with 8 H200 or B200
Models Up to ~32B at 4-8 bit 70B at 8-bit, plus smaller models 671B MoE, many large models
Power ~1.5-3 kW (estimate) ~7-8 kW for both servers (estimate) 10.2-14.3 kW per server
Cooling Air Air, check rack density Air or liquid, facility review required
Network 10-25 GbE 25 GbE 25 GbE front end, 400 Gb/s fabric only if models span servers
Local storage 2-4 TB NVMe 4-8 TB NVMe per server ~30 TB NVMe per server

Two servers in the medium tier is a deliberate choice: it lets you take one down for driver updates without losing the service. A single large server is a single point of failure. To turn concurrency targets into GPU counts, the self-hosted LLM cost post has a break-even model, and LLM tokens per second explains how speed per user falls as concurrency rises.

Lead times and procurement

GPU server lead times change with supply and are quote-specific, so we do not quote a number. Ask for a committed ship date in writing, and plan the rest of the schedule around it: electrical work for new circuits, rack and PDU delivery, and security review of the software often take as long as the server. In practice, the facilities work is the item teams start too late.

While you wait, rent the same GPU in a cloud to measure real concurrency and speed with your own prompts. Prefer the vendor's standard configurations; a custom build is slower to repair.

The software layer on top

Hardware arrives as bare metal. To deploy LLMs on premise you still need:

  1. OS and drivers. A supported Linux distribution, the NVIDIA data-center driver and CUDA (or ROCm on AMD), the NVIDIA Container Toolkit if you run containers, and Fabric Manager on NVSwitch-based 8-GPU systems. Pin versions; a driver update is a change, not a background task.
  2. An inference server that loads the model, batches requests and exposes an API. The vLLM vs Ollama comparison covers the main options.
  3. A gateway in front of the inference servers for API keys, quotas and routing across models.
  4. Monitoring for latency, tokens, errors and GPU memory, so you can see saturation before users do.
  5. Access control with SSO, roles, approval for which models get deployed and an audit log.

Building this from open source is a real option for teams with platform engineers to spare. AI Refinery, a self-hosted LLM platform, covers layers 2-5 on GPUs you provide: it installs inside your data center or an air-gapped network, deploys catalog models in a chosen quantization with one click, exposes each one as an OpenAI-compatible endpoint with tokens managed in the console, and adds a monitoring dashboard, RBAC, SSO, approval workflows and an audit log. Nothing phones home. Plans are sized by model, described in the pricing section. It does not supply the servers, the drivers or the facilities work above; those stay with you and your hardware vendor.

Pre-order checklist

  • Largest model and quantization chosen, GPU memory calculated with KV cache at peak concurrency
  • Form factor chosen: PCIe unless a model needs more than one server's worth of NVLink
  • Rack power budget, circuit voltage and UPS capacity confirmed with facilities
  • Cooling capacity confirmed for the full nameplate load
  • 25 GbE ports and a management network allocated
  • Local NVMe sized for every model, one previous version and staging
  • At least two servers if the service must survive maintenance
  • Driver, inference server, gateway, monitoring and access control owners named
  • Committed ship date in writing, and a cloud benchmark of your own prompts done

Questions about sizing for a specific site can go to [email protected].